1st Rough Plumbing Inspection (#1)
1st Rough Plumbing Inspection (#1)Scheduled For: 02-05-2026Is Assigned
Passed on 02-05-2026
| Assigned to Inspector: Steven Chmura |
02-05-2026See Violation Details in Comments
Complied02-05-2026
inspected the water service loops and sewer/building drains at back of building to inside for each unit
Courtesy Inspection (#1)Scheduled For: 10-24-2025Is Assigned
Closed on 10-23-2025
| Assigned to Inspector: Vincent McCrave |
Firewall Inspection Non-Res (#1)Scheduled For: 03-17-2026Is Assigned
Passed on 03-17-2026
| Assigned to Inspector: Peter Giverc |
Firewall Inspection Non-Res (#1)Scheduled For: 03-27-2026Is Assigned
Partial Passed on 03-27-2026
| Assigned to Inspector: Elizabeth BrownMcWatters |
03-27-2026See Violation Details in Comments
Transferred to Re-inspection03-27-2026
Partial for frame only
Firewall Inspection Non-Res (#2)Scheduled For: 04-01-2026Is Assigned
Partial Passed on 04-01-2026
| Assigned to Inspector: Elizabeth BrownMcWatters |
03-27-2026See Violation Details in Comments
Transferred to Re-inspection04-01-2026
Partial for frame only
04-01-2026See Violation Details in Comments
Transferred to Re-inspection04-01-2026
Partial for firewall leaving dollar tree still needing inspection.
Planet Fitness is completed and firewall inspected.
Firewall Inspection Non-Res (#3)
03-27-2026See Violation Details in Comments
Partial for frame only
04-01-2026See Violation Details in Comments
Partial for firewall leaving dollar tree still needing inspection.
Planet Fitness is completed and firewall inspected.
Footing Inspection (#1)Scheduled For: 10-21-2025Is Assigned
Passed on 10-21-2025PARTIAL
Rear wall
Footing Inspection (#2)
Footing Inspection (#1)Scheduled For: 10-29-2025Is Assigned
Passed on 10-29-2025
| Assigned to Inspector: Peter Giverc |
Footing Inspection (#1)Scheduled For: 10-31-2025Is Assigned
Passed on 10-31-2025PARTIAL
FOOTINGS BUILDING B & 3/4 OF BUILDING C
Footing Inspection (#2)Scheduled For: 11-04-2025Is Assigned
Partial Passed on 11-04-2025PARTIAL
| Assigned to Inspector: David Crum |
11-04-2025See Violation Details in Comments
Transferred to Re-inspection11-04-2025
5 footers marked on plans
Footing Inspection (#3)
11-04-2025See Violation Details in Comments
5 footers marked on plans
Frame Inspection (#1)Scheduled For: 03-05-2026
Partial Passed on 03-04-2026
ROOF PORTION- PART A
Frame Inspection (#2)Scheduled For: 03-17-2026Is Assigned
Passed on 03-17-2026
| Assigned to Inspector: Peter Giverc | PART A-ROOF PORTION
Frame Inspection (#1)Scheduled For: 04-01-2026Is Assigned
Passed on 04-01-2026
| Assigned to Inspector: Elizabeth BrownMcWatters |
Lintel Inspection (#1)Scheduled For: 10-24-2025Is Assigned
Partial Passed on 10-24-2025PARTIAL
David Crum
10-24-2025See Violation Details in Comments
Transferred to Re-inspection10-24-2025
inspection for stem wall 2.5 blocks high at wall against sprouts. marked on plans.
Lintel Inspection (#2)Scheduled For: 10-31-2025Is Assigned
Passed on 10-31-2025PARTIAL
2ND LIFT SIDE & REAR WALL BUILDING C
10-24-2025See Violation Details in Comments
Complied10-31-2025
inspection for stem wall 2.5 blocks high at wall against sprouts. marked on plans.
Lintel Inspection (#3)Scheduled For: 11-04-2025Is Assigned
Partial Passed on 11-04-2025
| Assigned to Inspector: David Crum |
11-04-2025See Violation Details in Comments
Transferred to Re-inspection11-04-2025
marked on plans.
Lintel Inspection (#4)Scheduled For: 11-12-2025Is Assigned
Passed on 11-12-2025
| Assigned to Inspector: Vincent McCrave |
11-04-2025See Violation Details in Comments
Complied11-12-2025
marked on plans.
11-12-2025See Violation Details in Comments
Complied11-12-2025
1st lift on separation wall between Bldg. B & C
Lintel Inspection (#1)Scheduled For: 11-14-2025Is Assigned
Partial Passed on 11-14-2025PARTIAL
| Assigned to Inspector: Mark Hammer |
Lintel Inspection (#2)Scheduled For: 11-18-2025Is Assigned
Passed on 11-18-2025PARTIAL
| Assigned to Inspector: Vincent McCrave |
11-18-2025See Violation Details in Comments
Complied11-18-2025
Inspection performed: 2nd lift for Shared walls Between Bldg. A & B, B & C and rear wall bldg. B.
-----
1st. lift rear wall bldg. A
Lintel Inspection (#3)Scheduled For: 11-19-2025Is Assigned
Passed on 11-19-2025
| Assigned to Inspector: Vincent McCrave |
Lintel Inspection (#1)Scheduled For: 11-20-2025Is Assigned
Passed on 11-20-2025
| Assigned to Inspector: Peter Giverc |
Lintel Inspection (#1)Scheduled For: 11-21-2025Is Assigned
Passed on 11-21-2025
| Assigned to Inspector: Peter Giverc |
Lintel Inspection (#1)Scheduled For: 11-24-2025Is Assigned
Passed on 11-24-2025PARTIAL
| Assigned to Inspector: Vincent McCrave |
11-24-2025See Violation Details in Comments
Complied11-24-2025
5th lift separation wall between Bldg. B & C, Separation wall between Bldg. A & B. -----
4th lift rear wall of bldg. B, West rear wall of Bldg. A..-----
1st lift west wall Bldg. A.
Lintel Inspection (#2)Scheduled For: 11-25-2025Is Assigned
Passed on 11-25-2025PARTIAL
| Assigned to Inspector: Peter Giverc |
Lintel Inspection (#3)Scheduled For: 11-26-2025Is Assigned
Passed on 11-26-2025PARTIAL
| Assigned to Inspector: Vincent McCrave |
11-26-2025See Violation Details in Comments
Complied11-26-2025
5th lift rear wall building B, 6th lift and top out at separation wall between bldg. A and B. passed
Lintel Inspection (#4)Scheduled For: 12-02-2025Is Assigned
Partial Passed on 12-02-2025
| Assigned to Inspector: Vincent McCrave |
12-02-2025See Violation Details in Comments
Transferred to Re-inspection12-02-2025
Top out rear wall bldg. A
Lintel Inspection (#5)Scheduled For: 12-04-2025Is Assigned
Canceled on 12-04-2025
| Assigned to Inspector: Vincent McCrave |
12-02-2025See Violation Details in Comments
Transferred to Re-inspection12-04-2025
Top out rear wall bldg. A
Lintel Inspection (#6)Scheduled For: 12-05-2025Is Assigned
Partial Passed on 12-05-2025
BEFORE 11 AM PLEASE
12-02-2025See Violation Details in Comments
Transferred to Re-inspection12-05-2025
Top out rear wall bldg. A
12-05-2025See Violation Details in Comments
Transferred to Re-inspection12-05-2025
3rd lift bldg. A west wall. passed
Lintel Inspection (#7)Scheduled For: 12-09-2025Is Assigned
Partial Passed on 12-09-2025
| Assigned to Inspector: Vincent McCrave |
12-02-2025See Violation Details in Comments
Transferred to Re-inspection12-09-2025
Top out rear wall bldg. A
12-05-2025See Violation Details in Comments
Transferred to Re-inspection12-09-2025
3rd lift bldg. A west wall. passed
12-09-2025See Violation Details in Comments
Transferred to Re-inspection12-09-2025
4th lift on west wall of bldg. A and top out of rear room on bldg. B. passed
Lintel Inspection (#1)Scheduled For: 12-09-2025Is Assigned
Waived on 12-09-2025
| Assigned to Inspector: Vincent McCrave |
Lintel Inspection (#8)Scheduled For: 12-11-2025Is Assigned
Passed on 12-11-2025PARTIAL
| Assigned to Inspector: Vincent McCrave |
12-02-2025See Violation Details in Comments
Complied12-11-2025
Top out rear wall bldg. A
12-05-2025See Violation Details in Comments
Complied12-11-2025
3rd lift bldg. A west wall. passed
12-09-2025See Violation Details in Comments
Complied12-11-2025
4th lift on west wall of bldg. A and top out of rear room on bldg. B. passed
12-11-2025See Violation Details in Comments
Complied12-11-2025
5th lift west wall of bldg. A.
Lintel Inspection (#9)
Lintel Inspection (#1)Scheduled For: 12-16-2025Is Assigned
Partial Passed on 12-16-2025
| Assigned to Inspector: Vincent G Artese |
12-16-2025See Violation Details in Comments
Transferred to Re-inspection12-16-2025
6th pour left side
Lintel Inspection (#2)Scheduled For: 12-19-2025Is Assigned
Passed on 12-19-2025
| Assigned to Inspector: Vincent McCrave |
12-16-2025See Violation Details in Comments
Complied12-19-2025
6th pour left side
12-19-2025See Violation Details in Comments
Complied12-19-2025
topout on westwall bldg. A
Rough Electric Inspection (#1)Scheduled For: 10-22-2025Is Assigned
Passed on 10-22-2025
| Assigned to Inspector: Jeremy Lentz |
Rough Mechanical Inspection (#1)
Rough Mechanical Inspection (#1)Scheduled For: 03-24-2026Is Assigned
Passed on 03-24-2026
| Assigned to Inspector: ANDREW F WALKER |
03-24-2026See Violation Details in Comments
Complied03-24-2026
Right side of structure 4 curb to red iron connection
Sheathing Inspection (#1)Scheduled For: 03-04-2026Is Assigned
Partial Passed on 03-04-2026PARTIAL
| Assigned to Inspector: Peter Giverc |<div><br></div><div>PART A ROOF PORTION</div>
Sheathing Inspection (#2)Scheduled For: 03-27-2026Is Assigned
Partial Passed on 03-27-2026
| Assigned to Inspector: Elizabeth BrownMcWatters | PM inspection requested Greg 352-497-6540
03-27-2026See Violation Details in Comments
Transferred to Re-inspection03-27-2026
Partial of nailing of planet fitness side.
Sheathing Inspection (#3)Scheduled For: 04-02-2026Is Assigned
| Assigned to Inspector: Mark Hammer |
03-27-2026See Violation Details in Comments
Partial of nailing of planet fitness side.
Slab Inspection (#1)Scheduled For: 03-18-2026Is Assigned
Passed on 03-18-2026
| Assigned to Inspector: Peter Giverc |
Slab Inspection (#1)Scheduled For: 10-21-2025Is Assigned
Canceled on 10-21-2025PARTIAL
| Assigned to Inspector: Vincent McCrave |
Slab Inspection (#2)
Slab Inspection (#1)
Slab Inspection (#1)Scheduled For: 02-20-2026Is Assigned
Passed on 02-20-2026
| Assigned to Inspector: Peter Giverc |<div><br></div><div>column grout only</div>
Slab Inspection (#2)Scheduled For: 02-24-2026Is Assigned
Passed on 02-24-2026
| Assigned to Inspector: Peter Giverc |
Slab Inspection (#1)Scheduled For: 03-17-2026Is Assigned
Passed on 03-17-2026
| Assigned to Inspector: Peter Giverc |
Bond Beam/Stemwall Inspection (#1)Scheduled For: 10-29-2025Is Assigned
Passed on 10-29-2025PARTIAL
| Assigned to Inspector: Peter Giverc |
Bond Beam/Stemwall Inspection (#2)
Partial Passed on 11-04-2025
11-04-2025See Violation Details in Comments
Transferred to Re-inspection11-04-2025
stem wall for demising walls. marked on plans.
Bond Beam/Stemwall Inspection (#3)
11-04-2025See Violation Details in Comments
stem wall for demising walls. marked on plans.
Structural Frame Inspection (#1)Scheduled For: 02-16-2026Is Assigned
Passed on 02-16-2026
| Assigned to Inspector: Peter Giverc |
T-Pole Inspection (#1)Scheduled For: 10-22-2025Is Assigned
Passed on 10-22-2025
| Assigned to Inspector: Jeremy Lentz |
T-Pole Power Release (#1)Scheduled For: 10-22-2025Is Assigned
Confirmed on 10-22-2025
BLD202506092 Owner Name: CORTA Lecanto LLC Inspection Passed on: 10/22/2025
Above Ceiling - Electrical Inspection (#1)
Structural Steel Certificate (#1)