1st Rough Plumbing Inspection (#1)
1st Rough Plumbing Inspection (#1)Scheduled For: 11-05-2025Is Assigned
Partial Passed on 11-05-2025PARTIAL
| Assigned to Inspector: Steven Chmura |
11-05-2025See Violation Details in Comments
Transferred to Re-inspection11-05-2025
partial inspection of underground,grease trunk line and branch tees,need to verify traps where applicable at next underground inspection
1st Rough Plumbing Inspection (#2)
11-05-2025See Violation Details in Comments
partial inspection of underground,grease trunk line and branch tees,need to verify traps where applicable at next underground inspection
1st Rough Plumbing Inspection (#1)Scheduled For: 11-06-2025Is Assigned
Canceled on 11-06-2025PARTIAL
| Assigned to Inspector: Vincent McCrave |
11-06-2025See Violation Details in Comments
Transferred to Re-inspection11-06-2025
Not ready
1st Rough Plumbing Inspection (#2)
11-06-2025See Violation Details in Comments
Not ready
1st Rough Plumbing Inspection (#3)Scheduled For: 11-07-2025Is Assigned
Partial Passed on 11-07-2025
| Assigned to Inspector: Vincent McCrave |
11-07-2025See Violation Details in Comments
Transferred to Re-inspection11-07-2025
Sanitary, storm, grease drainage on north wall, passed.
1st Rough Plumbing Inspection (#4)Scheduled For: 11-10-2025Is Assigned
Canceled on 11-10-2025
| Assigned to Inspector: Steven Chmura |
11-07-2025See Violation Details in Comments
Transferred to Re-inspection11-10-2025
Sanitary, storm, grease drainage on north wall, passed.
11-10-2025See Violation Details in Comments
Transferred to Re-inspection11-10-2025
cancelled by contractor,not ready
1st Rough Plumbing Inspection (#5)Scheduled For: 11-12-2025Is Assigned
Partial Passed on 11-12-2025
| Assigned to Inspector: Steven Chmura | changed to partial pass as requested by Steve C
11-07-2025See Violation Details in Comments
Complied11-12-2025
Sanitary, storm, grease drainage on north wall, passed.
11-10-2025See Violation Details in Comments
Complied11-12-2025
cancelled by contractor,not ready
1st Rough Plumbing Inspection (#6)Scheduled For: 12-03-2025Is Assigned
Passed on 12-03-2025
| Assigned to Inspector: Vincent McCrave |
12-03-2025See Violation Details in Comments
Complied12-03-2025
This inspection was for sewer tie-in only.
2nd Rough Plumbing Inspection (#1)
2nd Rough Plumbing Inspection (#1)Scheduled For: 02-20-2026Is Assigned
Failed on 02-20-2026
| Assigned to Inspector: Vincent G Artese |
02-20-2026See Violation Details in Comments
Transferred to Re-inspection02-20-2026
Not ready.
2nd Rough Plumbing Inspection (#2)
02-20-2026See Violation Details in Comments
Not ready.
2nd Rough Plumbing Inspection (#1)Scheduled For: 02-23-2026Is Assigned
Passed on 02-23-2026
Courtesy Inspection (#1)Scheduled For: 10-22-2025Is Assigned
Closed on 10-22-2025
| Assigned to Inspector: Vincent McCrave |
Courtesy Inspection (#1)Scheduled For: 10-24-2025Is Assigned
Closed on 10-23-2025
| Assigned to Inspector: Vincent McCrave |
Courtesy Inspection (#1)Scheduled For: 10-29-2025Is Assigned
Passed on 10-29-2025
| Assigned to Inspector: Peter Giverc |
Courtesy Inspection (#1)Scheduled For: 10-31-2025Is Assigned
Closed on 10-31-2025
| Assigned to Inspector: Vincent McCrave |
10-31-2025See Violation Details in Comments
SEE LINTEL INSPECTIONS
Courtesy Inspection (#1)Scheduled For: 11-25-2025Is Assigned
Passed on 11-25-2025
| Assigned to Inspector: ANDREW F WALKER |
11-25-2025See Violation Details in Comments
Complied11-25-2025
Under ground 3 loops refrigerant lines.
Footing Inspection (#1)Scheduled For: 10-08-2025Is Assigned
Passed on 10-08-2025PARTIAL
| Assigned to Inspector: Vincent McCrave |perimeter footing partial
Footing Inspection (#2)Scheduled For: 10-22-2025Is Assigned
Passed on 10-22-2025
| Assigned to Inspector: Andrew J Mylrea |
10-22-2025See Violation Details in Comments
Complied10-22-2025
Loading bay, rear right corner and front 4 column bases passed 10/22.
Footing Inspection (#1)Scheduled For: 10-15-2025Is Assigned
Passed on 10-15-2025PARTIAL
| Assigned to Inspector: Vincent McCrave |
Footing Inspection (#2)Scheduled For: 03-25-2026Is Assigned
Passed on 03-25-2026
| Assigned to Inspector: Peter Giverc |<div><br></div><div>sustainability pad in far right rear of store</div>
Frame Inspection (#1)Scheduled For: 12-03-2025Is Assigned
Passed on 12-03-2025
| Assigned to Inspector: Vincent McCrave |
Frame Inspection (#1)Scheduled For: 12-30-2025Is Assigned
Canceled on 12-30-2025
| Assigned to Inspector: Peter Giverc |<div><br></div><div>not ready</div>
Frame Inspection (#2)Scheduled For: 12-31-2025Is Assigned
Passed on 12-31-2025
Frame Inspection (#1)Scheduled For: 02-03-2026Is Assigned
Passed on 02-03-2026
This inspection is for the covered canopy on the front of the building, to the right of the entrance way. Area is highlighted on the approved plan set, see page A900
02-03-2026See Violation Details in Comments
Complied02-03-2026
This inspection is for the covered canopy on the front of the building, to the right of the entrance way. Area is highlighted on the approved plan set, see page A900
Frame Inspection (#1)Scheduled For: 02-16-2026Is Assigned
Failed on 02-16-2026
| Assigned to Inspector: Peter Giverc |
02-16-2026See Violation Details in Comments
Transferred to Re-inspection02-16-2026
Several wall clips missing fasteners, clips missing altogether (east wall only) R106.4
Frame Inspection (#2)Scheduled For: 02-17-2026Is Assigned
Passed on 02-17-2026
| Assigned to Inspector: Peter Giverc |
02-16-2026See Violation Details in Comments
Complied02-17-2026
Several wall clips missing fasteners, clips missing altogether (east wall only) R106.4
Frame Inspection (#1)Scheduled For: 02-26-2026Is Assigned
Passed on 02-26-2026
| Assigned to Inspector: Peter Giverc |
Lintel Inspection (#1)Scheduled For: 10-24-2025Is Assigned
Partial Passed on 10-24-2025PARTIAL
David Crum
10-24-2025See Violation Details in Comments
Transferred to Re-inspection10-24-2025
first lift front and side walls. marked on plans.
Lintel Inspection (#2)Scheduled For: 10-27-2025Is Assigned
Passed on 10-27-2025PARTIAL
| Assigned to Inspector: Vincent McCrave |
10-24-2025See Violation Details in Comments
Complied10-27-2025
first lift front and side walls. marked on plans.
10-27-2025See Violation Details in Comments
Complied10-27-2025
2nd lift both sides.
Lintel Inspection (#3)Scheduled For: 10-31-2025Is Assigned
Passed on 10-31-2025PARTIAL
4th LIFT FRONT AND SIDES 2ND LIFT AT REAR.
Lintel Inspection (#4)Scheduled For: 11-04-2025Is Assigned
Partial Passed on 11-04-2025PARTIAL
| Assigned to Inspector: David Crum |
11-04-2025See Violation Details in Comments
Transferred to Re-inspection11-04-2025
marked onplans
Lintel Inspection (#5)
11-04-2025See Violation Details in Comments
marked onplans
Lintel Inspection (#1)Scheduled For: 11-06-2025Is Assigned
Passed on 11-06-2025PARTIAL
| Assigned to Inspector: Vincent McCrave |
11-06-2025See Violation Details in Comments
Complied11-06-2025
Top-out west south east walls and 4th lift north wall. passed
Lintel Inspection (#2)
Lintel Inspection (#1)Scheduled For: 11-10-2025Is Assigned
Passed on 11-10-2025
| Assigned to Inspector: Peter Giverc |
Lintel Inspection (#1)Scheduled For: 11-14-2025Is Assigned
Passed on 11-14-2025
For entry columns
Pre Electric Pre Final Inspection (#1)Scheduled For: 12-17-2025Is Assigned
Canceled on 12-17-2025
| Assigned to Inspector: Vincent McCrave |
Pre Electric Pre Final Inspection (#2)
Closed on 12-17-2025
Rough Electric Inspection (#1)Scheduled For: 02-09-2026Is Assigned
Passed on 02-09-2026
| Assigned to Inspector: ANDREW F WALKER |
02-09-2026See Violation Details in Comments
Complied02-09-2026
As noted on E200
Rough Electric Inspection (#1)Scheduled For: 02-25-2026Is Assigned
Passed on 02-25-2026
| Assigned to Inspector: Jeremy Lentz |
02-25-2026See Violation Details in Comments
Complied02-25-2026
all walls except men and womens bathrooms
Rough Electric Inspection (#1)Scheduled For: 03-18-2026Is Assigned
Passed on 03-18-2026
| Assigned to Inspector: Jeremy Lentz | <div>SPROUTS ELECTRIC ROUGH WALL IN - AM PLEASE</div><div>STEVE - 689-345-4406</div>
Rough Electric Inspection (#1)Scheduled For: 03-25-2026Is Assigned
Passed on 03-25-2026
| Assigned to Inspector: Jeremy Lentz |
Rough Electric Inspection (#1)Scheduled For: 04-02-2026Is Assigned
| Assigned to Inspector: Jeremy Lentz |
Sheathing Inspection (#1)Scheduled For: 01-13-2026Is Assigned
Passed on 01-13-2026
| Assigned to Inspector: Vincent McCrave |
Slab Inspection (#1)Scheduled For: 12-22-2025Is Assigned
Passed on 12-22-2025
| Assigned to Inspector: David Crum |
12-22-2025See Violation Details in Comments
Complied12-22-2025
back of store and perimeter. marked on plans. termite treat on site.
Slab Inspection (#1)Scheduled For: 12-23-2025Is Assigned
Passed on 12-23-2025
| Assigned to Inspector: Peter Giverc |
Slab Inspection (#1)Scheduled For: 12-24-2025Is Assigned
Passed on 12-23-2025PARTIAL
| Assigned to Inspector: Peter Giverc |
Slab Inspection (#2)
Slab Inspection (#1)Scheduled For: 01-05-2026Is Assigned
Passed on 01-05-2026
| Assigned to Inspector: Elizabeth BrownMcWatters |
Slab Inspection (#1)Scheduled For: 02-18-2026Is Assigned
Passed on 02-18-2026
| Assigned to Inspector: Vincent G Artese |
02-18-2026See Violation Details in Comments
Complied02-18-2026
Steel dumpster pad.
Slab Inspection (#1)Scheduled For: 02-20-2026Is Assigned
Passed on 02-20-2026
| Assigned to Inspector: Peter Giverc |
Bond Beam/Stemwall Inspection (#1)Scheduled For: 10-22-2025Is Assigned
Passed on 10-22-2025
| Assigned to Inspector: Andrew J Mylrea |
10-22-2025See Violation Details in Comments
Complied10-22-2025
3 sides of main building passed 10/22
Bond Beam/Stemwall Inspection (#1)Scheduled For: 10-27-2025Is Assigned
Passed on 10-27-2025
T-Pole Inspection (#1)Scheduled For: 12-17-2025Is Assigned
Passed on 12-17-2025
T-Pole Power Release (#1)Scheduled For: 12-17-2025Is Assigned
Confirmed on 12-17-2025
BLD202504617 Owner Name: SPROUTS Inspection Passed on: 12/17/2025
Wire Lath Inspection (#1)Scheduled For: 04-01-2026Is Assigned
Passed on 04-01-2026
| Assigned to Inspector: Elizabeth BrownMcWatters |
Above Ceiling - Electrical Inspection (#1)Scheduled For: 02-09-2026Is Assigned
Passed on 02-09-2026
| Assigned to Inspector: ANDREW F WALKER |
02-09-2026See Violation Details in Comments
Complied02-09-2026
As noted on E200
Above Ceiling - Plumbing Inspection (#1)Scheduled For: 02-23-2026Is Assigned
Passed on 02-23-2026
| Assigned to Inspector: Steven Chmura |
Above Ceiling - Mechanical Inspection (#1)Scheduled For: 02-12-2026Is Assigned
Passed on 02-12-2026
| Assigned to Inspector: ANDREW F WALKER |
Underground Electric Inspection (#1)Scheduled For: 10-22-2025Is Assigned
Passed on 10-22-2025
Underground Electric Inspection (#1)Scheduled For: 12-02-2025Is Assigned
Partial Passed on 12-02-2025
| Assigned to Inspector: Jeremy Lentz |
Underground Electric Inspection (#2)Scheduled For: 12-10-2025Is Assigned
Partial Passed on 12-10-2025
| Assigned to Inspector: ANDREW F WALKER | As Noted on plan sheet E200.
Underground Electric Inspection (#3)
Closed on 12-18-2025
Underground Electric Inspection (#1)Scheduled For: 12-17-2025Is Assigned
Passed on 12-17-2025
Structural Steel Certificate (#1)