BOND BEAM/STEMWALL (#1)Scheduled For: 10-21-2010
Passed on 10-21-2010
1ST ROUGH PLUMB (#1)Scheduled For: 04-14-2010
Passed on 04-14-2010
SLAB (#1)Scheduled For: 04-20-2010Is Assigned
Passed on 04-20-2010
LINTEL (#1)Scheduled For: 05-24-2011
Closed on 05-24-2011
***IS THIS REQUIRED??***KIME
05-24-2011OTHER
Frame construction, no lintel inspection needed.
SHEATHING (#1)Scheduled For: 11-29-2010
Passed on 11-29-2010
11-29-2010OTHER-GENERAL ALL TYPES
Walls and roof.
ROUGH ELECTRICAL (#1)Scheduled For: 04-11-2011
Passed on 04-11-2011
ROUGH MECHANICAL (#1)Scheduled For: 04-11-2011
Passed on 04-11-2011
2ND ROUGH PLUMBING (#1)Scheduled For: 03-04-2011
Passed on 03-04-2011
GAS ROUGH (#1)Scheduled For: 05-24-2011
Closed on 05-24-2011
***IS THIS REQAUIRED??***KIME
STRUCTURAL FRAME (#1)Scheduled For: 04-11-2011
Passed on 04-11-2011
FRAME (#1)Scheduled For: 04-11-2011
Passed on 04-11-2011
04-11-2011CORRECT & PROCEED
8' special order doors to garage will be put in after drywall.
ROOFING (#1)Scheduled For: 11-09-2012Is Assigned
Passed on 11-09-2012
INSULATION (#1)Scheduled For: 05-24-2011
Passed on 05-24-2011
DRYWALL AND FIREWALL (#1)Scheduled For: 11-28-2011
Passed on 11-28-2011
WATER TIE IN [SUINSPKEY=1078] (#1)Scheduled For: 04-17-2013Is Assigned
Passed on 04-17-2013
PM INSPECTION APPRECIATED
FINAL BUILD (#1)Scheduled For: 04-17-2013Is Assigned
Passed on 04-17-2013
PM INSPECTION APPRECIATED
FINAL INSULATION (#1)Scheduled For: 04-17-2013Is Assigned
Passed on 04-17-2013
PM INSPECTION APPRECIATED
FINAL PLUMBING (#1)Scheduled For: 04-17-2013Is Assigned
Passed on 04-17-2013
PM INSPECTION APPRECIATED
FINAL ELECTRIC (#1)Scheduled For: 04-17-2013Is Assigned
Passed on 04-17-2013
PM INSPECTION APPRECIATED
FINAL MECH (#1)Scheduled For: 04-17-2013Is Assigned
Passed on 04-17-2013
PM INSPECTION APPRECIATED
PRE ELECTRIC PRE FINAL (#1)Scheduled For: 05-24-2012
Passed on 05-24-2012
PRE ELECTRIC PRE FINAL (#2)Scheduled For: 06-13-2012
Passed on 06-13-2012
****REQUESTING ANOTHER INSPECTION PER PROGRESS ENERGY REQUEST****KIME
FOOTER (#1)Scheduled For: 01-20-2010
Passed on 01-20-2010
01-20-2010CORRECT & PROCEED
Owner is working with architech on revision at garage for wall without offset and pads changed. He will submit revision to Building Department. Everything OK to pour footer.
DRY-IN INSPECTION (#1)Scheduled For: 12-07-2010
Passed on 12-07-2010
12-07-2010CORRECT & PROCEED
Penitrations in roof need to be checked at final roof inspection. Owner wants to get dryed in, but unable to get trades completed at this time. GTL.
90 DAY EXTENSION (#1)
Passed on 03-12-2008
90 DAY EXTENSION (#2)
Passed on 09-01-2009
90 DAY EXTENSION (#3)
Closed on 04-22-2023
90 DAY EXTENSION (#4)
Passed on 05-23-2012
RESIDENTIAL C.O. ISSUED (#1)Scheduled For: 04-17-2013
Passed on 04-17-2013
T-POLE [SUINSPKEY=3206] (#1)Scheduled For: 11-26-2008
Failed on 11-26-2008
11-26-2008TEMP POWER POLE MISC
250.52
T-POLE [SUINSPKEY=3206] (#2)Scheduled For: 12-01-2008
Passed on 12-01-2008
T-POLE [SUINSPKEY=3206] (#3)Scheduled For: 04-27-2010Is Assigned
Passed on 04-27-2010
SEWER TIE IN [SUINSPKEY=3209] (#1)Scheduled For: 04-17-2013Is Assigned
Passed on 04-17-2013
PM INSPECTION APPRECIATED