PERMIT SEARCH PORTAL
Details

Identification

Permit Number
BLD202404155
Type
New SFD - New Sfd
Added On
03-27-2024 11:26 AM
Declared Value
$200,000.00


Status (Closed)

Expires On
04-29-2025
Issued On
06-19-2024
Final On
10-31-2024
Certified On
11-13-2024


Description of Work

Build new single family home ** NOC IN OR BK 3466 PG 1817 ** SITE APPROVED FOR NEW SFD ONLY- MUST RETAIN A MIN OF 4 TREES**



Site Information

Primary Address
11661 N KENLAKE CIR DUNNELLON, FL 34434
Other Linked
1817100200133500020 CITRUS SPRINGS UNIT 20
17
18
01
13350
0020


Contacts

Contacts

Licensed Contact Primary EMPIRE CONSTRUCTION MANAGEMENT LLC 910 NE 8TH AVE OCALA, FL 34470

Property Owner Empire Construction Management LLC 910 NE 8TH AVE OCALA, FL 34470

Licensed Contact FRIENDLY HOME REPAIR LLC 5160 SE 135TH STREET SUMMERFIELD, FL 34491

Licensed Contact WEST MARION AIR COND & HEATING 510 NW RIDGEWOOD RD DUNNELLON, FL 34431

Licensed Contact SUN STATE POWER LLC 4682 SE 134TH STREET BELLEVIEW, FL 34420



Progress

Reviews
Permit Specialist Review Approved

Addressing Review Approved

Engineering FFEA Review Waived
Notarized affidavit in file, proposed finished floor will be set at minimum twelve (12) inches higher than the highest point of adjacent roadway(s).
Environmental Health Review Approved
SEPTIC SYSTEM APPROCAL MUST BE PROVIDED AT TIME OF FINAL INSPECTION PRIOR TO CO ISSUANCE
Plans Examiner Review Request for Information

Additional Information

05-10-2024DigEplan Review
1- Front door on energy calcs state EAST, site plan has front door facing WEST. Worst case not given. Adjust calcs to match site plan FBCE 403.7.1<div><br></div>

Driveway Review Approved
Swaled apron to follow existing grade. No roadway or edge of pavement damage present.
Site Review Request for Information

Additional Information

05-17-2024BUILDING & SITE DO NOT MATCH
The site plan needs to reflect the plan set. The back side of the home and back patio dimensions do not match the plan set dimension.&nbsp;

05-17-2024SITE MISC
Driveway apron needs to be drawn on the site plan

Utility Review Approved

Review Consolidation Request for Information
| Assigned to Reviewer: Gabe Donovan gabe.donovan@citrusbocc.com |
Review Distribution Approved
| Assigned to Reviewer: Gabe Donovan gabe.donovan@citrusbocc.com |
Plans Examiner Review Approved
| Assigned to Reviewer: Stephen R Switzer stephen.switzer@citrusbocc.com |
Site Review Request for Information
| Assigned to Reviewer: JENNIFER N GRIFFIN jennifer.griffin@citrusbocc.com |
Additional Information

06-13-2024SITE MISC
Previous site denial comment not addressed. The driveway apron needs to be drawn on the site plan for any property adjacent to a Public road.&nbsp;

Review Consolidation Request for Information
| Assigned to Reviewer: Gabe Donovan gabe.donovan@citrusbocc.com |
Review Distribution Approved
| Assigned to Reviewer: Gabe Donovan gabe.donovan@citrusbocc.com |
Site Review Approved
SITE APPROVED FOR NEW SFD ONLY- MUST RETAIN A MIN OF 4 TREES**
Review Consolidation Approved
| Assigned to Reviewer: Gabe Donovan gabe.donovan@citrusbocc.com |
Pre Permit Issuance Review Add Fees
| Assigned to Reviewer: Gabe Donovan gabe.donovan@citrusbocc.com |
Pre Permit Issuance Review Approved
| Assigned to Reviewer: Gabe Donovan gabe.donovan@citrusbocc.com |
NOC Review Approved
| Assigned to Reviewer: Gabe Donovan gabe.donovan@citrusbocc.com |
Environmental Health Final Review Approved

Land Assessment Review Complete

Finalization Review Request for Information

Additional Information

11-01-2024ADDITIONAL DOCUMENTS REQUIRED
Need health final approval and blower door to issue CO.

Blower Door Test Approved

Insulation Affidavit Approved

Finalization Review Approved
| Assigned to Reviewer: Beverly Gonzalez |

Conditions

Inspections
1st Rough Plumbing Inspection (#1)Scheduled For: 06-21-2024Is Assigned Passed on 06-21-2024
| Assigned to Inspector: Steven Chmura |
2nd Rough Plumbing Inspection (#1)Scheduled For: 08-08-2024Is Assigned Passed on 08-08-2024
| Assigned to Inspector: Steven Chmura |
Dry-In Inspection (#1)Scheduled For: 08-02-2024Is Assigned Passed on 08-02-2024
| Assigned to Inspector: DAVID CRUM |
Engineering Erosion Control Inspection (#1) Waived on 06-20-2024
<p class="MsoNormal"><a name="_Hlk159590737"></a><a name="_Hlk159304001"></a><a name="_Hlk156544648"></a><a name="_Hlk156564901"></a>We have waived this inspection so you may continue forward on your project. <br> <b>Please be sure to have erosion control measures in place throughout the construction process to prevent offsite sediment and stormwater runoff.</b> <br> Based on our review<a name="_Hlk151035484">, it doesn’t appear that construction activity would affect any Wetlands, Waterways, and/or the County’s Stormwater Drainage System. <br> </a>An inspection may be added later if we receive a complaint and/or observe offsite impacts. <o:p></o:p></p> <p class="MsoNormal"><o:p>&nbsp;</o:p></p> <p class="MsoNormal"><a name="_Hlk151035337">Erosion control measures are required to be in place as soon as any ground disturbance begins and maintained throughout the construction process. <o:p></o:p></a></p> <p class="MsoNormal">Erosion control measures such as a vegetative buffer, silt fence, or any appropriate Best Management Practice, as described in the Florida Stormwater Erosion and Sedimentation Control Manual, may be used. The manual can be downloaded at <a href="https://www.fsesci.com/downloads/">https://www.fsesci.com/downloads/</a> <o:p></o:p></p> <p class="MsoNormal">A vegetative buffer is the most efficient and cost-effective form of erosion control. For most sites, a minimum of 15 ft of undisturbed vegetation is a sufficient buffer. Steep sites may require a larger buffer area. A vegetative buffer can be reestablished on a disturbed site with the installation of sod. Silt fence is the most commonly used form of erosion control protection. Silt fence needs to be placed so that it includes all areas of fill or disturbed soils, and the silt fence needs to be keyed into the ground (buried up to the line, you should be able to pull up on the silt fence at any point and it does not move at the ground). Additional BPMs may be needed for sites with steep slopes.<o:p></o:p></p>
Final Building Inspection (#1)Scheduled For: 10-30-2024Is Assigned Canceled on 10-30-2024
| Assigned to Inspector: VINCENT G ARTESE |
Violations

10-30-2024See Violation Details in Comments Transferred to Re-inspection10-30-2024
See final electric

Final Building Inspection (#2)Scheduled For: 10-31-2024Is Assigned Passed on 10-31-2024
| Assigned to Inspector: Scott McGroarty |
Violations

10-30-2024See Violation Details in Comments Complied10-31-2024
See final electric

Final Driveway Apron Inspection (#1)Scheduled For: 10-30-2024Is Assigned Passed on 10-30-2024

Final Electric Inspection (#1)Scheduled For: 10-30-2024Is Assigned Failed on 10-30-2024
| Assigned to Inspector: Jeremy Lentz |
Violations

10-30-2024See Violation Details in Comments Transferred to Re-inspection10-30-2024
1. CONDENSING UNIT IS RATED FOR MAX 25AMP BREAKER. 30AMP INSTALLED 2. SMOKE/CARBON MONOXIDE DETECTOR REQUIRED OUTSIDE OF BEDROOMS.

Final Electric Inspection (#2)Scheduled For: 10-31-2024Is Assigned Passed on 10-31-2024
| Assigned to Inspector: Scott McGroarty |
Violations

10-30-2024See Violation Details in Comments Complied10-31-2024
1. CONDENSING UNIT IS RATED FOR MAX 25AMP BREAKER. 30AMP INSTALLED 2. SMOKE/CARBON MONOXIDE DETECTOR REQUIRED OUTSIDE OF BEDROOMS.

Final Mechanical Inspection (#1)Scheduled For: 10-30-2024Is Assigned Canceled on 10-30-2024
| Assigned to Inspector: VINCENT G ARTESE |
Violations

10-30-2024See Violation Details in Comments Transferred to Re-inspection10-30-2024
See violation on breaker size on AC unit

Final Mechanical Inspection (#2)Scheduled For: 10-31-2024Is Assigned Passed on 10-31-2024
| Assigned to Inspector: Scott McGroarty |
Violations

10-30-2024See Violation Details in Comments Complied10-31-2024
See violation on breaker size on AC unit

Final Plumbing Inspection (#1)Scheduled For: 10-30-2024Is Assigned Failed on 10-30-2024
| Assigned to Inspector: VINCENT G ARTESE |
Violations

10-30-2024See Violation Details in Comments Transferred to Re-inspection10-30-2024
Toilet bases need to be sealed

Final Plumbing Inspection (#2)Scheduled For: 10-31-2024Is Assigned Passed on 10-31-2024
| Assigned to Inspector: Scott McGroarty |
Violations

10-30-2024See Violation Details in Comments Complied10-31-2024
Toilet bases need to be sealed

Final Utilities Residential Inspection (#1)Scheduled For: 10-30-2024Is Assigned Passed on 10-30-2024
| Assigned to Inspector: TIMOTHY J HUDSON | Final passed
Frame Inspection (#1)Scheduled For: 07-26-2024Is Assigned Canceled on 07-26-2024
| Assigned to Inspector: DAVID CRUM |
Violations

07-26-2024See Violation Details in Comments Transferred to Re-inspection07-26-2024
meant to schedule str frame.check str frame notes

Frame Inspection (#2)Scheduled For: 08-14-2024Is Assigned Failed on 08-14-2024
| Assigned to Inspector: DAVID CRUM |
Violations

07-26-2024See Violation Details in Comments Transferred to Re-inspection08-14-2024
sliding glass door not sealed per fbcr703.4 garage door not installed.

Frame Inspection (#3)Scheduled For: 08-16-2024Is Assigned Passed on 08-16-2024
| Assigned to Inspector: DAVID CRUM |
Violations

07-26-2024See Violation Details in Comments Complied08-16-2024
sliding glass door not sealed per fbcr703.4 garage door not installed.

Lintel Inspection (#1)Scheduled For: 07-09-2024Is Assigned Passed on 07-09-2024
| Assigned to Inspector: DAVID CRUM |
Pre Electric Pre Final Inspection (#1) Closed on 11-01-2024
Jamie sent email on 11/1/24 @ 10:18am<div><br></div><p class="MsoNormal">Hello, <o:p></o:p></p><p class="MsoNormal"><o:p>&nbsp;</o:p></p><p class="MsoNormal">Can you please remove the pre-final electric inspection&nbsp;on permit BLD202404155?<o:p></o:p></p><p class="MsoNormal"><o:p>&nbsp;</o:p></p><p> </p><p class="MsoNormal">Thank you<br clear="all"> <o:p></o:p></p>
Final Power Release (#1)Scheduled For: 10-31-2024Is Assigned Confirmed on 10-31-2024
BLD202404155 Owner Name: EMPIRE CONSTRUCTION MANAGEMENT LLC Inspection Passed on: 10/31/2024
Rough Electric Inspection (#1)Scheduled For: 08-08-2024Is Assigned Passed on 08-08-2024
| Assigned to Inspector: Philip Charnock |
Rough Mechanical Inspection (#1)Scheduled For: 08-08-2024Is Assigned Passed on 08-08-2024
| Assigned to Inspector: Philip Charnock |
Sheathing Inspection (#1)Scheduled For: 07-26-2024Is Assigned Passed on 07-26-2024
| Assigned to Inspector: DAVID CRUM |
Slab Inspection (#1)Scheduled For: 06-25-2024Is Assigned Passed on 06-25-2024
| Assigned to Inspector: VINCENT G ARTESE |
Structural Frame Inspection (#1) Passed on 07-26-2024

Violations

07-26-2024See Violation Details in Comments Complied07-26-2024
nail A01 two rows 9" o.c. fix sheathing in valley by front door. walked with framer on site. will check at frame.

TUG Meter Inspection (#1)Scheduled For: 08-08-2024Is Assigned Passed on 08-08-2024
| Assigned to Inspector: Philip Charnock |
TUG Meter Power Release (#1)Scheduled For: 08-08-2024Is Assigned Confirmed on 08-08-2024
BLD202404155 Owner Name: EMPIRE CONSTRUCTION MANAGEMENT LLC Inspection Passed on: 8/8/2024
Final Roof Inspection (#1)Scheduled For: 10-30-2024Is Assigned Passed on 10-30-2024
| Assigned to Inspector: VINCENT G ARTESE |
Insulation Inspection (#1)Scheduled For: 08-16-2024Is Assigned Passed on 08-16-2024
| Assigned to Inspector: DAVID CRUM |