Deck & Bond Inspection (#1)Scheduled For: 12-19-2023Is Assigned
Canceled on 12-19-2023
| Assigned to Inspector: Dawson Retter |
Deck & Bond Inspection (#2)Scheduled For: 12-19-2023Is Assigned
Passed on 12-19-2023
| Assigned to Inspector: VINCENT MCCRAVE | ** UNABLE TO MEET SCHEDULED REQUEST **
Engineering Erosion Control Inspection (#1)
Waived on 11-01-2023
<p class="MsoNormal">We have waived this inspection so you may continue forward
on your project. <br>
<b>Please be sure to have erosion control measures in place throughout the
construction process to prevent offsite sediment and stormwater runoff.</b> <br>
Based on our review, it doesn’t appear that construction activity would affect
any wetlands/waterways, and/or our stormwater drainage system. <br>
An inspection may be added later if we receive a complaint and/or observe
offsite impacts. <o:p></o:p></p>
<p class="MsoNormal"><o:p> </o:p></p>
<p class="MsoNormal">Erosion control measures are required to be in place as soon
as any ground disturbance begins and maintained throughout the construction
process Additional inspections may be added later if we receive a complaint
and/or observe offsite impacts. <o:p></o:p></p>
<p class="MsoNormal">Erosion control measures such as a vegetative buffer, silt
fence, or any appropriate Best Management Practice, as described in the Florida
Stormwater Erosion and Sedimentation Control Manual, may be used. The manual
can be downloaded at <a href="https://www.fsesci.com/downloads/">https://www.fsesci.com/downloads/</a>
<o:p></o:p></p>
<p class="MsoNormal">A vegetative buffer is the most efficient and cost-effective
form of erosion control. For most sites, a minimum of 15 ft of undisturbed
vegetation is a sufficient buffer. Steep sites may require a larger buffer
area. A vegetative buffer can be reestablished on a disturbed site with the
installation of sod. Silt fence is the most commonly used form of erosion
control protection. Silt fence needs to be placed so that it includes all areas
of fill or disturbed soils, and the silt fence needs to be keyed into the
ground (buried up to the line, you should be able to pull up on the silt fence
at any point and it does not move at the ground). Additional BPMs may be needed
for sites with steep slopes.<o:p></o:p></p>
<p class="MsoNormal"><o:p> </o:p></p>
Final Building Inspection (#1)
Pool Steel Inspection (#1)Scheduled For: 11-01-2023Is Assigned
Passed on 11-01-2023
| Assigned to Inspector: DAVID CRUM |
Final Electric Inspection (#1)