1st Rough Plumbing Inspection (#1)Scheduled For: 11-01-2023Is Assigned
Failed on 11-01-2023
| Assigned to Inspector: Steven Chmura |
11-01-2023See Violation Details in Comments
Transferred to Re-inspection11-01-2023
must have county approved plans on jobsite,with county stamp of approval on each page
1st Rough Plumbing Inspection (#2)Scheduled For: 11-02-2023Is Assigned
Passed on 11-02-2023
| Assigned to Inspector: Steven Chmura |
11-01-2023See Violation Details in Comments
Complied11-02-2023
must have county approved plans on jobsite,with county stamp of approval on each page
2nd Rough Plumbing Inspection (#1)Scheduled For: 04-18-2024Is Assigned
Passed on 04-18-2024
| Assigned to Inspector: Steven Chmura |
Dry-In Inspection (#1)Scheduled For: 04-22-2024Is Assigned
Passed on 04-22-2024
| Assigned to Inspector: Andrew J Mylrea |
04-22-2024See Violation Details in Comments
Complied04-22-2024
Doc box destroyed.
Re-post permit and NOC.
Underground Electric Inspection (#1)
Waived on 11-13-2023
Engineering Erosion Control Inspection (#1)
Waived on 10-24-2023
<p class="MsoNormal">We have waived this inspection so you may continue forward
on your project. <br>
<b>Please be sure to have erosion control measures in place throughout the
construction process to prevent offsite sediment and stormwater runoff.</b> <br>
Based on our review, it doesn’t appear that construction activity would affect
any wetlands/waterways, and/or our stormwater drainage system. <br>
An inspection may be added later if we receive a complaint and/or observe
offsite impacts. <o:p></o:p></p>
<p class="MsoNormal"><o:p> </o:p></p>
<p class="MsoNormal">Erosion control measures are required to be in place as soon
as any ground disturbance begins and maintained throughout the construction
process Additional inspections may be added later if we receive a complaint
and/or observe offsite impacts. <o:p></o:p></p>
<p class="MsoNormal">Erosion control measures such as a vegetative buffer, silt
fence, or any appropriate Best Management Practice, as described in the Florida
Stormwater Erosion and Sedimentation Control Manual, may be used. The manual
can be downloaded at <a href="https://www.fsesci.com/downloads/">https://www.fsesci.com/downloads/</a>
<o:p></o:p></p>
<p class="MsoNormal">A vegetative buffer is the most efficient and cost-effective
form of erosion control. For most sites, a minimum of 15 ft of undisturbed
vegetation is a sufficient buffer. Steep sites may require a larger buffer
area. A vegetative buffer can be reestablished on a disturbed site with the
installation of sod. Silt fence is the most commonly used form of erosion
control protection. Silt fence needs to be placed so that it includes all areas
of fill or disturbed soils, and the silt fence needs to be keyed into the
ground (buried up to the line, you should be able to pull up on the silt fence
at any point and it does not move at the ground). Additional BPMs may be needed
for sites with steep slopes.<o:p></o:p></p>
Final Building Inspection (#1)
Final Driveway Apron Inspection (#1)
Final Electric Inspection (#1)
Final Gas Inspection (#1)
Final Mechanical Inspection (#1)
Final Plumbing Inspection (#1)
Frame Inspection (#1)Scheduled For: 06-06-2024Is Assigned
Failed on 06-06-2024
| Assigned to Inspector: VINCENT MCCRAVE |
06-06-2024See Violation Details in Comments
Transferred to Re-inspection06-06-2024
DUCT BLOCKS ACCESS TO ATTIC FROM THE ATTIC ACCESS OPENING ON 2ND FLOOR, PLEASE CHOOSE A NEW LOCATION.
FIREBLOCKING REQ. AT DROP CEILING IN KITCHEN WHERE DROP CEILING MEETS FURRED EXT. WALL.
FIREBLOCKING REQ IN UTILITY WHERE SOFFIT IS LOCATED.
06-13-2024See Violation Details in Comments
Fire blocking not done cited by previous inspector.
Frame Inspection (#2)Scheduled For: 06-13-2024Is Assigned
Failed on 06-13-2024
| Assigned to Inspector: VINCENT G ARTESE |
06-06-2024See Violation Details in Comments
Transferred to Re-inspection06-13-2024
DUCT BLOCKS ACCESS TO ATTIC FROM THE ATTIC ACCESS OPENING ON 2ND FLOOR, PLEASE CHOOSE A NEW LOCATION.
FIREBLOCKING REQ. AT DROP CEILING IN KITCHEN WHERE DROP CEILING MEETS FURRED EXT. WALL.
FIREBLOCKING REQ IN UTILITY WHERE SOFFIT IS LOCATED.
Frame Inspection (#3)
Passed on 06-25-2024
06-06-2024See Violation Details in Comments
Complied06-25-2024
DUCT BLOCKS ACCESS TO ATTIC FROM THE ATTIC ACCESS OPENING ON 2ND FLOOR, PLEASE CHOOSE A NEW LOCATION.
FIREBLOCKING REQ. AT DROP CEILING IN KITCHEN WHERE DROP CEILING MEETS FURRED EXT. WALL.
FIREBLOCKING REQ IN UTILITY WHERE SOFFIT IS LOCATED.
Lintel Inspection (#1)Scheduled For: 11-30-2023Is Assigned
Passed on 11-30-2023
| Assigned to Inspector: DAVID CRUM |
Rough Electric Inspection (#1)Scheduled For: 06-03-2024Is Assigned
Passed on 06-03-2024
| Assigned to Inspector: Jeremy Lentz |
Rough Gas Inspection (#1)Scheduled For: 04-18-2024Is Assigned
Passed on 04-18-2024
| Assigned to Inspector: Steven Chmura |
Rough Mechanical Inspection (#1)Scheduled For: 04-19-2024Is Assigned
Passed on 04-19-2024
| Assigned to Inspector: JOHN S NASUTA |
Sheathing Inspection (#1)Scheduled For: 02-06-2024Is Assigned
Passed on 02-06-2024
| Assigned to Inspector: VINCENT MCCRAVE |
Slab Inspection (#1)Scheduled For: 11-13-2023Is Assigned
Passed on 11-13-2023
| Assigned to Inspector: SCOTT A SCHNETTLER |
Structural Frame Inspection (#1)Scheduled For: 02-29-2024Is Assigned
Failed on 02-29-2024
| Assigned to Inspector: VINCENT MCCRAVE |
02-29-2024See Violation Details in Comments
Transferred to Re-inspection02-29-2024
2X4 door bucks req tapcons.
Detail C/S2 2 rows of blocking req. for int. bearing walls over 8' 6".
See notes on Floorplan for placement of HTT4, HTT5, LTTP2 ON ALL STUD PACKS, OPENS AND CORNERS for both floors.
Engineered floor truss bracing (strongbacks) are required to be the same species lumber or better than the truss.
Truss F16 2x6 strongback in wrong location.
Threaded rod (go bolt system) is not according to plan, no changes can be made with out engineer approval as stated in plan notes. please anchor the 2nd floor walls according to plan details.
Truss Girders A7 & A8, 5ply & 4ply require additional structural screws at the junction points on both top and bottom chord. A7 requires screws both sides, see truss eng. detail for screw sizes.
Structural Frame Inspection (#2)Scheduled For: 04-16-2024Is Assigned
Passed on 04-16-2024
| Assigned to Inspector: VINCENT MCCRAVE |
02-29-2024See Violation Details in Comments
Complied04-16-2024
2X4 door bucks req tapcons.
Detail C/S2 2 rows of blocking req. for int. bearing walls over 8' 6".
See notes on Floorplan for placement of HTT4, HTT5, LTTP2 ON ALL STUD PACKS, OPENS AND CORNERS for both floors.
Engineered floor truss bracing (strongbacks) are required to be the same species lumber or better than the truss.
Truss F16 2x6 strongback in wrong location.
Threaded rod (go bolt system) is not according to plan, no changes can be made with out engineer approval as stated in plan notes. please anchor the 2nd floor walls according to plan details.
Truss Girders A7 & A8, 5ply & 4ply require additional structural screws at the junction points on both top and bottom chord. A7 requires screws both sides, see truss eng. detail for screw sizes.
T-Pole Inspection (#1)Scheduled For: 12-21-2023Is Assigned
Passed on 12-21-2023
| Assigned to Inspector: JOHN S NASUTA |
T-Pole Power Release (#1)Scheduled For: 12-21-2023Is Assigned
Confirmed on 12-21-2023
BLD202319621 Owner Name: CANARIO MARISSA Inspection Passed on: 12/21/2023
Wire Lath Inspection (#1)Scheduled For: 06-25-2024Is Assigned
Passed on 06-25-2024
Final Roof Inspection (#1)Scheduled For: 08-12-2024Is Assigned
Canceled on 08-12-2024
| Assigned to Inspector: VINCENT MCCRAVE |
08-12-2024See Violation Details in Comments
Transferred to Re-inspection08-12-2024
According to plans, sheet 4, an off ridge vent is included in the calculations. please verify with engineer if it is required or only a recommendation.
Final Roof Inspection (#2)Scheduled For: 08-20-2024Is Assigned
Canceled on 08-20-2024
| Assigned to Inspector: VINCENT MCCRAVE |
08-12-2024See Violation Details in Comments
Transferred to Re-inspection08-20-2024
According to plans, sheet 4, an off ridge vent is included in the calculations. please verify with engineer if it is required or only a recommendation.
Final Roof Inspection (#3)Scheduled For: 09-13-2024Is Assigned
Passed on 09-16-2024
| Assigned to Inspector: VINCENT MCCRAVE |
08-12-2024See Violation Details in Comments
Complied09-16-2024
According to plans, sheet 4, an off ridge vent is included in the calculations. please verify with engineer if it is required or only a recommendation.
Insulation Inspection (#1)Scheduled For: 08-09-2024Is Assigned
Passed on 08-09-2024
| Assigned to Inspector: VINCENT MCCRAVE |